Sunday, July 24, 2011

PEX rough-in complete

We finished up the PEX rough-in on the lower level. This stuff is so easy to run. Next week we'll cut over our existing fixtures and start running the system full time. Hopefully it is leak free!

We also started the lower level HVAC. We only have 4 vents to put in so it shouldn't be too hard. There's still a page long list of odds and ends that need to be completed, but hopefully in another week (or maybe two) all our rough-ins will be complete and we can call for an inspection. We'll be just a few weeks shy of 6 months from the time we got our building permits. The project is moving along a bit faster than I thought it would.